Network Maintenance: reload and upgrade network switch a-wells-frg-hall-3-1-c9300-48 on Thursday, June 18, 2026 between 3 AM and 5:30 AM

Scheduled Maintenance Report for ITS Network & Systems

Completed

The scheduled maintenance has been completed.
Posted Jun 18, 2026 - 05:30 PDT

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jun 18, 2026 - 03:00 PDT

Scheduled

Datacom/Netmon has scheduled the following network maintenance:

What: reload network switch a-wells-frg-hall-3-1-c9300-48.
When: Thursday, June 18, 2026 between 3 AM and 5:30 AM
Scope: reload the switch to upgrade the IOS software code from an outdated code to the current standard code.
Impact: loss of wired and wireless network connectivity to network switch a-wells-frg-hall-3-1-c9300-48 for approx 30 minutes.
The switch is located at Wells Fargo Hall TR3.1.
Posted Jun 13, 2026 - 11:03 PDT
This scheduled maintenance affected: Network.